GOSHEN IRRIGATION DISTRICT

GID HOMEPAGE
    
Sign Up for GID's Online Water System.
Members must fill out the Online form prior to using the Online System.
Click here to download the form (requires MS Word)
 
 
 Check out the Goshen Irrigation District Facebook page for news and water updates!
 
Contact the office to sign up for our TEXT ALERTS to be notified of water delivery changes and new information in your area 
 
 
 
We would like to provide an update on the Fort Laramie Canal Tunnel 2 Rehabilitation Project and the progress being made at the site. Significant work has been completed over the past several months, and crews continue moving forward on multiple phases of construction.

To date, crews have completed major excavation activities at the Tunnel 2 inlet and outlet areas, installed slope stabilization systems, and completed substantial temporary shotcrete work to stabilize the excavation walls during construction. The shotcrete currently visible on the excavation faces is temporary and will ultimately be covered or replaced as permanent structural components are completed. In addition, the Tunnel 2 inlet structure has now been completed.

At the outlet structure, crews have reached final grade and have been actively tying reinforcing steel, building structural wall forms, and preparing for major concrete pours. Work is progressing simultaneously on several sections of the outlet transition structure, and the site continues to take shape each week. In addition, crews have also started preparing portions of the Tunnel 1 outlet laydown area in order to stay ahead on future phases of the overall project.

While substantial progress has been made, the project has experienced some unforeseen challenges. During excavation and stabilization work, crews encountered areas of loose sandy material that have continued to ravel and slough off the excavation walls. These ground conditions have made it more difficult and time consuming to properly install and shoot shotcrete in certain locations while maintaining safe working conditions.

As a result of these conditions, portions of the work have taken longer than originally anticipated, which has impacted the initial construction schedule. At this time, the originally anticipated June 15th completion target will be adjusted, with project operations potentially being pushed back to June 29th at the soonest.

The contractor, engineers, and Goshen Irrigation District continue working closely together to minimize delays while ensuring the project is completed safely and correctly. We understand the importance of the irrigation season and are making every effort to advance construction as efficiently as possible.

We appreciate everyone’s patience and understanding as this critical rehabilitation project moves forward. Additional updates will continue to be provided as progress continues.

 
 

 

GID currently has approximately 76,385 acre-feet (AF) of water in storage, which equates to approximately 56 days for the district, as of June 4th, and is tentatively planning to start water at Whalen on June 29th. This equates to an estimated allocation of approximately 0.70 acre-feet per acre. To help stretch the limited supply and maximize irrigation days, delivery rates may need to average around 0.80 CFS per 100 acres, which is roughly equal to 1 CFS per 120 acres.

 
 
 

 
 
 
 
Fort Laramie Canal Tunnel Groundbreaking Ceremony Marks Major Milestone for Regional Water Infrastructure. 
 
On October 28, 2025, the Goshen Irrigation District , in partnership with Gering Fort Laramie Irrigation District, hosted a groundbreaking ceremony to celebrate the launch of the Fort Laramie Canal Tunnel Rehabilitation Project.
 
The event began with a project overview at the Goshen Irrigation District office in Torrington, followed by a site visit to Tunnel 2 inlet along the Fort Laramie Canal. Attendees included local and state officials, engineering and construction partners, and community members who gather to commemorate the start of a project that will restore and reinforce a vital irrigation system serving thousands of acres of farmland across Wyoming and Nebraska.
 
Speakers at the event reflected on the 2019 collapse of Tunnel No. 2, which disrupted agricultural operations and underscored the importance of resilient infrastructure. Remarks from representatives of the irrigation districts, the bureau of reclamation, and the Select Water Committee emphasized the collaborative spirit and technical expertise that made the project possible.
 
Following the ceremonial shovel turn at the project site, guests returned to the Goshen Irrigation District office for luncheon and community networking.
 
The Fort Laramie Canal Tunnel Rehabilitation Project represents a significant investment in agricultural productivity, water security, and regional resilience. Construction will begin soon, with continued support from local, state, and federal partners.
 
For more information, please contact:
 
Goshen Irrigation District
Kevin Strecker, Manager 
Phone: 307-532-7031
Email: kevin.strecker@goshenirrigation.com